Mountain Outreach 2005

Monday, July 4

Great day on the work site. Weather was not too bad, with a light rain briefly at lunch time to cool things off for a few minutes.

They day began at 6:00 with our full work force heading to the site. Site preparation needs were extensive, so everyone followed the early schedule. In short order, the ground was smoothed and tents were erected for the saw area, food preparation, rest, and beverages.

All four walls exterior walls were up by noon. The house is under roof. Ninety percent of the wire has been pulled.

The insulation crew heads out tomorrow morning at 6:00, followed by dry wall crew and others at 7:00.

Check back tomorrow for more details and photos.

< Sunday | Monday | Tuesday | Wednesday | Thursday | Friday>
< Overview>

Photos are arranged into galleries organized by time.
Click on any photo below to visit the gallery starting at the indicated time.


Photos beginning
07/04/05
06:32


Photos beginning
07/04/05
07:27


Photos beginning
07/04/05
11:29


Photos beginning
07/04/05
14:46


College Park Baptist Church home page