Mountain Outreach 2007

Tuesday, July 3

Good weather means good working conditions, and we enjoyed both today.

Early morning saw the roofing team shingling the roof. The electrical team finished pulling all wire except range and dryer, insulation was installed in all walls and under the floor, and we proceeded with dry wall installation and mudding throughout the house.

The house has a second coat of paint on the exterior.

Early tomorrow morning flooring will be installed and the ceiling sprayed.

MO2007 Main Page
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday

 

Photos are arranged into thumbnail groups organized by time.
Click for slide show, or
click on any photo below to visit the group starting at the indicated time.

Photos beginning 06:49

Group 1:
Photos beginning
07/03/07, 06:49
Photos beginning 08:19

Group 2:
Photos beginning
07/03/07, 08:19
Photos beginning 08:47

Group 3:
Photos beginning
07/03/07, 08:47
Photos beginning 09:12

Group 4:
Photos beginning
07/03/07, 09:12
Photos beginning 10:21

Group 5:
Photos beginning
07/03/07, 10:21
Photos beginning 12:02

Group 6:
Photos beginning
07/03/07, 12:02
Photos beginning 14:34

Group 7:
Photos beginning
07/03/07, 14:34
Photos beginning 16:24

Group 8:
Photos beginning
07/03/07, 16:24
Photos beginning 19:13

Group 9:
Photos beginning
07/03/07, 19:13

College Park Baptist Church home page