Thanks to all who contributed their time and efforts to make this trip possible. Please follow our daily progress on this site. Highlights of the day are usually posted by midnight.
Monday: Contruction begins. First exterior wall raised just after noon. All exterior walls are now in place, and two interior stud walls have been constructed.
First wall at 12:17.
Tuesday: Trusses in place, roof on. Very sturdy construction. Generous donations from Fresh Market and Bojangles -- thanks!
Wednesday: The home is now weather-tight, with all doors and windows in, and shingles on. Althought storms were in the area most of the day, we only had a tiny sprinkle during the workday. Major storms came through around 6:00 p.m., accompanied by local flooding. But the job site was unharmed; even the tents were not disturbed.
Thursday. Last night's storm drenched the worksite, but left no damage. The sandy soil drained quickly. Vinyl siding is complete and the HVAC unit is installed.
Friday. Mission trip complete. We dedicated the home this afternoon and presented the keys to Ms. House. We cherish the chance to get to know her and her community.