Another day with great weather. Dry wall was installed and mudded last evening. It was a late evening for this crew, as they had to wait for the plumbers to catch up due to their starting work later than scheduled.
Interior painting began this morning, after a light sanding of the dry wall mud.
Permanent electric power was connected at 11:00 a.m., and all wiring, light fixtures, and receptacles except those for range and dryer were installed and tested by 3:00 p.m. today.
Most of the exterior trim is now in place.
Vinyl flooring was laid late afternoon, and doors are being installed this evening.
The house is taking shape.
Thanks for all your prayers.